Homerton College - New Shower Doors
| Company: |
Homerton College |
| Location: |
Halls of Residence – Cambridge CB2 |
| Project Type: |
80 Shower Doors |
| Value: |
£70,800 |
We were approached by The Facilities Manager of Homerton College with a view to updating 240 number Shower Doors within the Halls of Residence over a period of three years the first being 80 number which were installed in July 2010 with a further 80 to be fitted in 2011 and the final 80 in 2012.
Scope of Works
- Remove old shower doors
- Clearance from site
- Installation of 80 New Formica faced shower doors
End result
This being a working college we had to carry out these works with the least disruption to the college working time table therefore it was agreed these works would take place during non term time. However, the Halls of Residence is often hired out during non term time and therefore we had to liaise carefully with the Facilities Manager to ensure that we did not interfere with these functions. Obviously it was essential that all Building and Health & Safety requirements were adhered to and we supplied only first class tradesmen to carry out all the elements of this project. Due to the college annual budget allocation these works have been spread over three years.
Back to case studies
|